Warwick Armory Facility Improvements
©Warwick Armory Facility Improvements
RGB has been commissioned to provide investigative, design, and construction administration services to repair and improve Building #3 of the RI National Guard’s Warwick Armory, as it suffered major damage during a large winter snowstorm last year. RGB was commissioned for their forensic skills of identifying areas of water infiltration and slab/foundation wall separation.
Our team has submitted an investigative report to RIARNG for approval and recently completed documents for bidding and construction.
Findings of RGB’s conditions assessment report included water infiltration through the exterior of the building, improper subsurface conditions causing the floor slab to cave in on itself, and aged conditions of many building components.
The scope of work includes repairs and improvements to the building assessment, including the exterior façade and insulation, windows, doors, ceilings floors, masonry foundation, overall lighting in the latrines, gymnasium, classroom, supply rooms, and all common areas.
This project will follow a moderately fast-tracked design schedule, estimated to be completed over a five-month period.